Section III - Report on Projects Operating with Treasury Board Approval - DPR - 2014-15
- Project costs and actual expenditures include Employee Benefit Plans (EBP) and exclude taxes.
- Projects listed have been identified as either:
- those in which the estimated expenditure exceeds the delegated approval authority granted to the Department of National Defence (DND) by the Treasury Board (TB) ($30 million with substantive cost estimates), or;
- those in which the risk is particularly high, regardless of the estimated amounts.
- Main estimates column: For Accrual Based Projects, the numbers are based on the reprofile submission and/or standalone submissions that were approved on or before Annual Reference Level Updates (ARLU) 2014-15 cut-off date.
- Total authorities: Same as Planned Spending.
- Original Estimated Total Cost is defined as the costs comprised of four components of Vote 5 funding:
- Procurement costs of the acquisition (equipment platform/system/fleet and associated infrastructure);
- Integrated Logistics Support (nominally two year spares Initial Provisioning, training development, technical data packages, simulators, etc - will vary from project to project);
- Project Management Office costs to include project staff SWE/military pay, Travel, Training, Office Space, contracted support, etc; and
- GST.
Project Number | Project Title |
Project Phase | Original Estimated Total Cost (Net of taxes) | Revised Estimated Total Cost (Net of taxes) | Previous Year Expenditure (Net of taxes) | Actual Total Cost | 2014-15 Main Estimates |
2014-15 Planned Spending |
2014-15 Total Authorities |
2014-15 Actual Spending |
Pers GL Total | Actual EBP | Expected Date of Close-out |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Program: Defence Ready Force Element Production | |||||||||||||
NA | Joint Task Force 2 | I | 79,320,783 | 79,320,783 |
34,838,213 | 38,121,235 |
12,133,805 | 12,133,805 | 3,283,022 | March 2018 | |||
NA | Canadian Special Operations Regiment | I | 109,520,050 | 109,520,050 | 37,201,786 | 48,508,628 |
48,112,502 | 23,276,513 | 23,276,513 | 11,306,842 | March 2017 | ||
Program: Defence Capability Element Production | |||||||||||||
0086 | Operational Flight Program (OFP) | I | 151,410,100 | 151,410,100 | 98,972,924 | 103,118,225 |
3,089,000 | 3,089,000 | 4,145,301 | - | - | November 2015 | |
0113 | Advanced Distributed Combat Training System (ADCTS) | I | 200,696,174 | 200,696,174 | 172,567,139 | 172,676,426 |
109,000 | 109,000 | 109,287 | - | - | Closed | |
0140 | CP140 Aurora Incremental Modernization Project (AIMP) | I | 1,320,695,177 | 1,565,789,341 | 1,058,506,007 | 1,105,126,562 | 4,605,590 | 49,482,901 | 49,482,901 | 46,620,555 | December 2020 | ||
0273 | CF-18 Advanced Multi-role Infrared Sensor | I | 199,216,340 | 199,216,340 | 155,670,076 | 156,484,231 |
744,000 | 744,000 | 814,155 | - | - | May 2017 | |
0276 | Intelligence, Surveillance, Target Acquisition and Reconnaissance (ISTAR) 1 | D/I | 640,006,000 | 672,118,746 | 375,843,055 | 394,169,935 |
22,665,841 | 22,665,841 | 18,326,880 | 1,962,842 | 392,568 | September 2018 | |
0295 | Aurora Communications Management System (CMS) Replacement | I | 95,153,000 | 89,845,673 |
89,650,969 | 89,845,673 |
45,000 | 45,000 | 194,704 | - | - | March 2015 | |
0405 | Canadian Advanced Synthetic Environment (CASE) | I | 44,919,000 | 89,786,380 |
52,064,077 | 56,609,733 |
4,651,629 | 4,651,629 | 4,545,656 | 502,324 | 100,465 | September 2017 | |
0410 | Flight Deck Simulators (FDS) | I | 40,862,000 | 40,862,000 |
39,581,875 | 39,581,875 |
205,000 | 205,000 | - | March 2016 | |||
0436 | Close Combat Vehicles | C/O | 2,070,000,000 | 2,070,000,000 | 37,939,343 | 38,114,391 | 201,531 | 201,531 | 175,048 | - | - | Closed | |
0438 | Joint Space Support Project (JSSP) | I | 43,273,473 |
43,273,473 |
38,289,459 |
38,596,375 | 307,000 | 307,000 | 306,916 | - | - | Closed | |
0439 | Biological Warfare Threat Medical Countermeasures | I | 163,980,000 |
123,477,102 |
33,929,830 |
35,710,073 | 2,085,400 | 2,085,400 | 1,780,243 | 309,331 | 61,866 | March 2019 | |
0451 | Primrose Lake Evaluation Range TSPI System | I | 63,153,000 |
63,153,000 |
39,460,173 | 41,144,751 | 2,567,400 | 2,567,400 | 1,684,578 | 22,254 | 4,451 | September 2015 | |
0547 | Area Surveillance / Secondary Surveillance Radar (ASR/SSR) Project | I | 98,841,539 |
96,292,606 |
8,114,695 | 21,178,925 | 13,376,000 | 13,376,000 | 13,064,230 | 461,782 | 92,356 | March 2016 | |
0548 | Aerodrome Precision Approach and Landing System (APALS) | I | 54,721,000 |
55,074,000 |
48,871,932 | 49,056,394 | 239,431 | 239,431 | 184,462 | 105,475 | 21,095 | March 2016 | |
0562 | Close Area Suppression Weapon Imp | I | 126,156,000 |
151,079,000 | 129,560,777 | 133,742,630 | 4,169,665 | 4,169,665 | 4,181,853 | 407,724 | 81,545 | July 2016 | |
0609 | Fixed Wing Search and Rescue Aircraft Replacement Project (FWSAR)2 | D | 1,844,932,025 | 1,844,932,025 | 11,375,908 | 16,936,609 | 7,145,275 | 6,182,750 | 6,182,750 | 5,560,701 | 3,420,954 | 684,191 | 2023 |
0624 | Joint Information and Intelligence Fusion Capability (JIIFC) | I | 63,966,195 | 63,966,195 |
16,740,717 | 25,452,469 | 8,721,000 | 8,721,000 | 8,711,752 | 1,307,918 | 261,584 | December 2017 | |
0625 | Polar Epsilon Joint Space-Based Wide Area Surveillance and Support | I | 64,553,000 | 64,553,000 |
53,314,000 | 53,315,073 | - | - | 1,073 | - | - | Closed | |
0627 | CF-18 IMP Defensive Electronic Warfare | I | 187,705,966 | 187,705,966 | 145,918,872 | 151,359,097 | 4,665,000 | 4,665,000 | 5,440,225 | 380,130 | 76,026 | September 2016 | |
0646 | Omnibus Night Vision Capability Project (ONVC) | I | 54,246,000 | 54,246,000 |
31,057,888 | 35,334,086 | 4,612,000 | 4,612,000 | 4,276,198 | 22,254 | 4,451 | March 2017 | |
0743 | Tactical Control Radar (TCR) Modernization | D/I | 41,376,000 | 78,302,850 |
6,702,806 | 6,800,484 | 134,854 | 134,854 | 97,678 | - | - | March 2017 | |
0877 | Aircraft Arrestor Systems (AAS) Modernization | I | 54,797,414 | 54,797,414 |
43,811,593 | 46,841,304 | 3,094,983 | 3,094,983 | 3,029,711 | 33,042 | 6,608 | January 2016 | |
0965 | Aurora Structural Life Extension Project (ASLEP) | I | 279,547,271 | 417,279,557 | 240,497,319 | 257,887,898 | 61,337,445 | 18,001,611 | 18,001,611 | 17,390,579 | 513,940 | 102,788 | September 2019 |
1007 | Medium to Heavy Lift Helicopters | I | 2,022,258,000 | 2,312,902,792 | 1,709,882,942 | 1,808,253,528 | 356,276,142 | 102,617,348 | 102,617,348 | 98,370,586 | 6,938,927 | 1,387,785 | June 2018 |
1036 | Airlift Capability Project-Tactical | I | 3,006,650,000 | 3,068,209,460 | 2,595,861,985 | 2,695,720,563 | 147,551,243 | 88,269,645 | 88,269,645 | 99,858,578 | 2,435,603 | 487,121 | December 2016 |
1111 | CF Explosive Ordnance Disposal Team Equipment | I | 79,390,000 | 79,390,000 | 59,184,987 | 67,354,078 | 8,275,041 | 8,275,041 | 8,169,091 | 529,214 | 105,843 | March 2016 | |
1112 | Enhanced Counter Improvised Explosive Devices(EC-IED) | I | 186,095,220 | 179,512,517 | 118,894,019 | 125,614,566 | 9,197,000 | 9,197,000 | 6,720,547 | 1,220,953 | 244,191 | March 2018 | |
1117 | Airlift Capability Project- Strategic | I | 1,807,355,000 | 1,807,299,879 | 1,393,577,793 | 1,730,872,260 | - | 326,487,731 | 326,487,731 | 337,294,467 | 192,642 | 38,528 | December 2015 |
1199 | Expedient Route Opening Capability (EROC) | I | 184,312,000 | 184,312,000 | 165,319,451 | 165,319,451 | 15,000 | 15,000 | - | - | 2017 | ||
1204 | Light Armoured Vehicle Remote Weapon System | I | 51,892,000 | 51,892,000 |
46,838,000 | 47,063,718 | 226,000 | 226,000 | 225,718 | - | - | Closed | |
1210 | Mission Support Unit | I | 83,878,000 | 84,684,994 |
24,987,777 | 28,352,164 | 4,938,106 | 4,938,106 | 3,364,387 | 370,737 | 74,147 | March 2018 | |
1216 | Arctic/ Offshore Patrol Ship | I | 3,073,600,000 | 3,534,450,011 | 148,621,942 | 343,119,670 | 241,751,596 | 203,652,052 | 203,652,052 | 194,497,728 | 4,340,857 | 868,171 | 2024 |
1241 | Main Battle Tank | I | 650,000,000 | 650,000,000 | 427,131,253 | 488,110,131 | 173,627,408 | 75,418,854 | 75,418,854 | 60,978,878 | 1,984,700 | 396,940 | October 2017 |
1242 | IED Mineblast Protection Kit | I | 52,485,000 | 52,485,000 |
41,592,000 | 41,593,372 | 1,000 | 1,000 | 1,372 | - | - | Closed | |
1247 | Light Armoured Vehicle III Upgrade Project | D/I | 1,314,495,288 | 1,314,495,288 | 382,984,463 | 676,179,533 | 315,114,368 | 274,580,121 | 274,580,121 | 293,195,070 | 2,101,768 | 420,354 | June 2019 |
1259 | Interoperable Griffon Reconnaissance Escort Surveillance System (INGRESS ) | I | 66,910,169 | 66,910,169 |
57,561,178 | 58,276,026 | 1,937,000 | 1,937,000 | 714,848 | 22,254 | 4,451 | March 2015 | |
1336 | Canadian Surface Combatant Project (CSC)2 | D | 52,020,013 | 26,200,000,000 | 21,151,212 | 42,906,650 | 26,989,314 | 27,156,279 | 27,156,279 | 21,755,438 | 7,324,087 | 1,464,817 | 2043 |
1350 | Lightweight Towed Howitzer | I | 265,320,000 | 265,320,410 | 159,551,315 | 174,896,198 | 15,704,740 | 15,704,740 | 15,344,883 | 523,622 | 104,724 | March 2018 | |
1430 | Tactical Armoured Patrol Vehicle | I | 1,250,000,000 | 1,250,000,000 | 116,559,969 | 169,069,130 | 450,958,279 | 50,090,690 | 50,090,690 | 52,509,161 | 3,169,687 | 633,937 | 2018 |
1494 | Force Mobility Enhancement Project | D/I | 356,382,000 | 356,382,000 | 59,570,559 | 72,938,553 | 106,012,400 | 16,825,198 | 16,825,198 | 13,367,994 | 1,314,701 | 262,940 | April 2018 |
1576 | Military Personnel Management Capability Transformation | D | 204,574,683 | 204,555,512 | 17,756,514 | 33,012,903 | 24,695,965 | 15,431,615 | 15,431,615 | 15,256,389 | 5,489,341 | 1,097,868 | June 2020 |
1686 | Short Range Air-to-Air Missile (SRAAM) | I | 197,494,000 | 39,540,000 |
34,461,641 | 34,513,785 | 52,000 | 52,000 | 52,144 | - | - | December 2014 | |
2346 | Medium Support Vehicle System Project | I | 1,071,012,000 | 1,577,991,990 | 443,093,040 | 506,123,727 | 101,260,193 | 57,432,213 | 57,432,213 | 63,030,687 | 4,312,659 | 862,532 | December 2020 |
2371 | GPS Advanced Navigation and Precision Approach | I | 130,307,472 | 169,804,804 | 101,530,683 | 110,004,651 | 8,080,000 | 8,080,000 | 8,473,968 | 318,529 | 63,706 | March 2015 | |
2383 | Integrated Soldier System Platform | D | 316,347,148 | 316,347,148 | 18,034,876 | 20,411,077 | 2,637,361 | 2,637,361 | 2,376,201 | 1,427,706 | 285,541 | June 2021 | |
2523 | Mercury Global- MG | I | 526,069,716 | 439,265,928 | 136,154,461 | 228,785,313 | 100,030,144 | 100,030,144 | 92,630,852 | 1,155,492 | 231,098 | January 2017 | |
2549 | Submarine Capability Life Extension | I | 828,484,000 | 896,772,000 | 853,889,355 | 854,395,447 | 330,000 | 330,000 | 506,092 | 22,254 | 4,451 | March 2017 | |
2586 | Halifax Class Modernization/Frigate Equipement Life Extension (FELEX) | I | 1,129,251,000 | 2,758,179,000 | 1,536,485,832 | 1,806,879,536 | 284,484,064 | 279,845,740 | 279,845,740 | 270,393,704 | 16,379,145 | 3,275,829 | January 2019 |
2637 | Armoured Personnel Carrier Replacement | I | 2,355,707,000 | 2,355,707,000 | 2,282,290,000 | 2,284,068,121 | 1,560,000 | 1,560,000 | 1,778,121 | 83,515 | 16,703 | Closed | |
2640 | Improved Point Defence Missile | I | 480,600,000 | 504,400,000 | 500,312,000 | 500,555,065 | 100,000 | 100,000 | 243,065 | 195,862 | 39,172 | March 2015 | |
2657 | CC-150 Strategic Air-to-Air Refuelling (SAAR) | I | 138,989,000 | 138,989,000 | 140,102,080 | 140,122,463 | 20,652 | 20,652 | 20,383 | 11,833 | 2,367 | December 2015 | |
2659 | CF-18 Advanced Precision Guided Munition | I | 58,148,221 | 58,148,221 |
46,209,304 | 47,877,938 | 1,663,561 | 1,663,561 | 1,668,634 | 178,599 | 35,720 | May 2015 | |
2664 | SIRIUS - Electro-optic Sensor | I | 277,814,000 | 272,357,000 | 187,741,549 | 190,989,632 | 5,441,000 | 5,441,000 | 3,248,083 | 463,815 | 92,763 | July 2017 | |
2673 | Joint Support Ship | D | 2,328,783,765 | 2,328,783,765 | 126,907,595 | 189,395,153 | 59,234,505 | 59,234,505 | 62,487,558 | - | 2022 | ||
2678 | Canadian Search and Rescue Helicopter (CSH) Project | I | 784,954,000 | 784,954,000 | 776,390,255 | 778,690,255 | 1,600,000 | 1,600,000 | 2,300,000 | - | - | July 2016 | |
2680 | Maritime Helicopter Project (MHP) | I | 3,115,979,000 | 3,174,085,000 | 1,860,334,646 | 1,896,766,370 | 455,789,480 | 41,240,137 | 41,240,137 | 36,431,724 | 9,326,228 | 1,865,246 | 2022 |
2716 | LAV Recce Surveillance System Upgrade (LRSS UP) | D | 623,486,264 | 623,486,264 | 11,120,199 | 30,845,710 | 98,761,617 | 19,536,533 | 19,536,533 | 19,725,511 | 1,220,320 | 244,064 | March 2020 |
2754 | Advanced Medium Range Air-to-Air Missile | I | 145,807,000 | 145,807,000 | 90,682,120 | 91,808,459 | 1,124,885 | 1,124,885 | 1,126,339 | - | January 2016 | ||
2760 | Land Command Support System Life Extension (LCSS LE) | I | 276,668,313 | 276,668,313 | 120,476,692 | 169,398,144 | 70,584,705 | 49,385,030 | 49,385,030 | 48,921,452 | 1,028,467 | 205,693 | March 2018 |
2790 | Maritime Integrated Network Management System | D | 59,521,000 | 61,254,000 |
1,710,044 | 1,849,978 | 116,000 | 116,000 | 139,934 | 115,056 | 23,011 | December 2021 | |
2803 | Protected Military Satellite Communications | I | 555,229,448 | 555,229,448 | 408,398,652 | 422,122,798 | 24,223,585 | 17,204,625 | 17,204,625 | 13,724,146 | 1,061 | 212 | March 2021 |
2877 | Point Defense Missile System Upgrade (PMDSU)2 | D | 801,985,860 | 801,985,860 | - | 66,661,894 | 64,250,000 | 64,250,000 | 66,661,894 | 10,679 | 2,136 | December 2030 | |
3667 | Surveillance of Space | I | 97,499,000 | 97,499,000 |
87,887,871 | 88,454,090 | 565,800 | 565,800 | 566,219 | 19,280 | 3,856 | Closed | |
5832 | CF-18 Engineering Change Proposal 583R2 | I | 445,537,042 | 445,537,042 | 367,874,643 | 380,186,329 | 11,126,773 | 11,126,773 | 12,311,686 | 646,059 | 129,212 | March 2017 | |
Various | Canadian Cryptographic Modernization Program | D/I | 838,607,000 | 838,607,000 | 228,013,091 | 295,105,176 | 82,844,472 | 82,844,472 | 67,092,084 | 2020 | |||
Various | Clothe the Soldier Omnibus | I | 180,884,000 | 375,928,000 | 313,266,000 | 315,826,589 | 3,587,818 | 3,587,818 | 2,560,589 | 194,850 | 38,970 | September 2018 | |
Various | CF CBRN Defence Omnibus | D | 295,313,000 | 285,837,000 | 106,886,000 | 116,841,530 | 9,955,530 | 1,461,548 | 292,310 | March 2022 | |||
1228 | 5 Wing Goose Bay Remediation Project3 | I | 296,555,716 | 296,555,716 | 62,066,703 | 72,298,085 | 10,963,018 | 10,963,018 | 72,298,085 | 932,354 | 186,471 | March 2020 | |
0487 | Distant Early Warning Line Clean-Up Project4 | I | 583,273,000 | 583,273,000 | 553,856,595 | 558,959,785 | 6,437,147 | 6,437,147 | 5,103,189 | 1,174,946 | 234,989 | March 2017 | |
4360 | Esquimalt - FMF Cape Breton Shops Consolidation5 | I | 534,830,000 | 534,830,000 | 109,735,871 | 169,290,900 | 60,100,000 | 60,100,000 | 59,555,029 | 119,577 | 23,915 | December 2020 | |
TOTAL: PROGRAM ACTIVITIES | 42,086,961,012 | 71,778,481,473 | 21,981,380,591 | 24,206,963,714 | 2,951,168,669 | 2,256,683,831 | 2,256,683,831 | 2,287,649,826 | 88,208,896 | 17,641,779 |
Legend: D = Definition, I = Implementation, C/O = Close-Out, FOC = Full Operational Capability, EPC = Effective Project Closure
Instructions
Original estimated total cost: The total cost estimate for the project in the original Treasury Board decision.
Revised estimated total cost: The most recent Treasury Board decision for the total cost estimate for the project.
Actual total cost: All expenditures to date, including the reporting year.
Main Estimates: The amount of funding sought through the Main Estimates process.
Planned spending: The amount should include any updates to funding provided through the Main Estimates (i.e., Supplementary Estimates).
Total authorities: The project authorities for the reporting year, as approved by the Treasury Board.
Actual spending: Total amount spent during the reporting year.
Expected date of close-out: The year that the project is expected to be completed.
Notes:
- Project LF Intelligence, Surveillance, Target Acquisition and Reconnaissance (ISTAR) Omnibus (276) includes the totals from subprojects 1013, 1014, 1015, 1277 and 1278.
- For the Fixed Wing Search and Rescue Aircraft Replacement (FWSAR), the Canadian Surface Combatant (CSC), and the Point Defence Missile System Upgrade (PDMSU) projects, expenditure authority was approved, without Project Approval (PA) being granted. Revised estimated total costs report the full Project Approval, although they have yet to be approved.
- Expenditures: this project pre-dated DRMIS (2010-11) so expenditures from pre-DRMIS are based on various project reports (not DRMIS or FMAS). TB granted PPA for this Omnibus project and delegated Expenditure Authority to Minister of National Defence (MND). All Sub-projects have now been granted EPA by MND.
- Expenditures: this project pre-dated DRMIS (2010-11), so expenditures from pre-DRMIS, are based on various project reports (not DRMIS). -- This project only moved onto DRMIS under WBS C.00487 on 1 April 2014).
- The project construction completion is expected by end FY 2017-18 and close out will be two years later.