Opinion of probable cost: Centre Block project due diligence report: Cost report

Document navigation for "Centre Block project due diligence report: Cost report"

This Opinion of Probable Cost outlines the hard construction costs for both the restoration and modernization of the Centre Block and construction of the Parliament Welcome Centre as per the summary table noted below:

Opinion of probable cost
Cost Breakdown Centre Block Cost Parliament Welcome Centre Cost
Net Building Cost of Construction $1,540,065,366 $447,896,093
General Requirements + Construction Management Fees + Bonds and Insurance $462,019,610 $118,657,414
Subtotal Construction Estimate $2,002,084,976 $566,553,507
Design Contingency (25%) $385,016,342 (15%) $67,184,414
Construction Contingency (20%) $308,013,073 (10%) $44,789,609
Subtotal Without Escalation $2,695,114,391 $678,527,530
Hard Cost Escalation $304,877,241 $54,179,000
Total Hard Construction Estimate $2,999,991,632 $732,706,530