Burlington Canal Lift Bridge: Bridge deck replacement project

Find out about the deck replacement project for the existing Burlington Canal Lift Bridge.

On this page

Project overview

Location

Burlington, Ontario
Locate the Burlington Canal Lift Bridge on a map

Type of project

Replacement

Lead department

Public Services and Procurement Canada

Design and engineering consultant

AECOM Canada Ltd.

Construction manager

EllisDon Civil Ltd. and Chant Ltd., in joint venture

Project cost

$32.5 million

Project status

Phase 1 and 2: complete

Next steps

Site clean-up, restoration and demobilization

Project description

About the bridge

The Burlington Canal Lift Bridge provides access to thousands of motorists and pedestrians entering Hamilton Harbour.

Replacement project

This project involved replacing the existing bridge deck. The 3 main objectives for this project are described below:

It is anticipated that this project will extend the life of key components of the bridge by approximately:

This project will improve the overall operations of the bridge, extend its lifespan and ensure the continued safety of bridge users.

The design and engineering tender was posted on buyandsell.gc.ca in early November 2021 and closed on December 21, 2021. The design and engineering contract was awarded to AECOM Canada Ltd. on January 21, 2022.

The construction management tender was posted on buyandsell.gc.ca on April 12, 2022, and closed on June 3, 2022. The construction management contract was awarded to EllisDon Civil Ltd. and Chant Ltd., in joint venture, on June 21, 2022.

Project phases

The 2 phases of this project are described below.

Phase 1: Removing and replacing the existing bridge deck

Phase 1 of the project included replacing the lift span deck.

This work began during the winter 2022 to 2023 seasonal shutdown (late December 2022 to March 2023) and continued through the rest of 2023.

Work accelerated during the winter 2024 seasonal shutdown (January to March 2024) and was completed in time to reopen for marine navigation.

A bridge closure was required from January to March 2024 to complete phase 1 of the project, replacing the lift span deck, and to begin phase 2, rehabilitating the approach spans. During this time, the bridge was closed to motorists, cyclists and pedestrians.

Phase 2: Rehabilitating the bridge approach spans and widening localized sections of the sidewalk

Phase 2 of the project included rehabilitating the approach spans.

This work began during the winter 2024 seasonal shutdown (January to March 2024) and will continue into fall 2024.

Once the concrete decks were removed, we rehabilitated the existing structural steel.

One lane remained open for alternating traffic until completion. During this period:

Public notices about the closures will be issued in advance and shared through our social media channels. This will ensure that the public is aware of each closure and its impact on local traffic. The same information will be distributed to stakeholders for further broadcasting.

Photo gallery

Photo of the decking being bolted down and  the vehicular barrier being installed on the Burlington Canal Lift Bridge

Phase 1—The west side of the lift span deck is being replaced on the Burlington Canal Lift Bridge.

Photo of the decking being bolted down and  the vehicular barrier being installed on the Burlington Canal Lift Bridge

Phase 1—The decking on the Burlington Canal Lift Bridge is being bolted down and the vehicular barrier is being installed. 

Photo of asphalt being removed on the south approach of the Burlington Canal Lift Bridge as construction workers prepare for demolition with machinery

Phase 2—Asphalt is being removed to prepare for demolition on the south approach of the Burlington Canal Lift Bridge.

Key milestones

Project background

Engaging with stakeholders

In early 2020, we started work on a concept design to replace the bridge deck. While developing the preliminary design, we advised and consulted with the key stakeholders affected by the project:

We ensured that stakeholders were regularly consulted throughout the planning process.

Initial meetings with stakeholders were held in May and July 2021.

Latest news about this project

July 7, 2022: Government of Canada awards construction management contract for Burlington Canal Lift Bridge deck replacement

Related links

Page details

Date modified: