The governments of Canada and British Columbia have approved a new list of projects under the Clean Water and Wastewater Fund (CWWF), which supports the rehabilitation of community drinking water and wastewater infrastructure and the planning and design of future systems that meet drinking water and wastewater effluent standards.
The Government of Canada allocated $225,067,721 to British Columbia under the CWWF and will fund up to 50 per cent of the eligible project costs. The Government of British Columbia will provide up to $148.5 million and will fund 33 per cent of the eligible project costs. With local governments providing the remainder, a combined total of $450 million will provide B.C. families with clean and reliable drinking water and wastewater services.
As part of the bilateral agreement between Canada and British Columbia, the following 144 projects have now been approved for federal funding amounting to more than $186.6 million. Combined with provincial funding of nearly $123.2 million and local government contributions of over $63.4 million, more than $373.2 million will be going toward projects across the province.
These projects are in addition to the 35 CWWF projects announced on September 30, 2016 as part of the signing of the Canada-British Columbia bilateral agreement.
Location |
Project Name |
Federal Funding |
Provincial Funding |
Municipal Funding |
Anticipated Start Date |
100 Mile House |
Alpine Water System Upgrade |
$984,425 |
$649,720 |
$334,705 |
2017-04-1 |
Abbotsford |
Gladwin Siphon Inlet, Odour Control and Outlet Chamber Project |
$995,000 |
$656,700 |
$338,300 |
2017-06-1 |
Anmore |
Optimization of Stormwater Assets |
$137,500 |
$90,750 |
$46,750 |
2017-03-1 |
Armstrong |
Wastewater Treatment Plant Rehabilitation |
$316,500 |
$208,890 |
$107,610 |
2017-04-15 |
Ashcroft |
Village of Ashcroft – 2016 Sewage Treatment Plant Upgrade Dewatering Centrifuge |
$265,000 |
$174,900 |
$90,100 |
2017-08-1 |
Balfour |
Balfour Water System Upgrade & Universal Metering Project |
$1,698,500 |
$1,121,010 |
$577,490 |
2017-05-1 |
Bamfield |
Bamfield Water Treatment Facility |
$848,900 |
$560,274 |
$288,626 |
2017-01-9 |
Boston Bar |
FVRD Electoral Area A: Boston Bar Water Systems Upgrade |
$52,972 |
$34,961 |
$18,011 |
2017-07-3 |
Burnaby |
Combined Sewer Separation Program 2017 |
$2,943,080 |
$1,942,432 |
$1,000,648 |
2017-04-1 |
Castlegar |
Water System Efficiency Plan |
$30,000 |
$19,800 |
$10,200 |
2017-02-1 |
Chetwynd |
Water Treatment Plant Upgrades |
$1,566,095 |
$1,033,623 |
$532,473 |
2017-01-5 |
Chilliwack |
Yarrow Waterworks Reservoir "A" Replacement |
$850,000 |
$561,000 |
$289,000 |
2017-06-1 |
Christina Lake |
Christina Lake Water System Upgrades |
$402,500 |
$265,650 |
$136,850 |
2017-03-1 |
Clearwater |
Water Supply Well No. 3 and Water Supply Main |
$1,053,000 |
$694,980 |
$358,020 |
2017-01-1 |
Clearwater |
Clearwater Septage Receiving Station Equalization Basin |
$140,000 |
$92,400 |
$47,600 |
2017-05-1 |
Clinton |
Clinton Water Supply Main Replacement |
$587,500 |
$387,750 |
$199,750 |
2017-03-1 |
Coldstream |
Coldstream Sewer Line Extension |
$65,000 |
$42,900 |
$22,100 |
2017-04-1 |
Comox Valley |
Comox Valley Water Supply System Treatment Project |
$2,626,500 |
$1,733,490 |
$893,010 |
2017-01-1 |
Coquitlam |
Plateau Water Pump Station Project |
$2,900,000 |
$1,914,000 |
$986,000 |
2017-03-1 |
Courtenay |
Black Creek Oyster Bay Water Supply Security Project |
$340,250 |
$224,565 |
$115,685 |
2017-06-1 |
Cumberland |
Cumberland Water Treatment and Supply Improvements |
$3,005,000 |
$1,983,300 |
$1,021,700 |
2017-03-1 |
Delta |
South Delta Groundwater Well Feasibility Study |
$25,000 |
$16,500 |
$8,500 |
2017-01-01 |
Duncan |
Cowichan Water Supply Structured Decision Model (SDM) Development |
$100,000 |
$66,000 |
$34,000 |
2016-12-16 |
Duncan |
Sustainable Watershed Systems, through Asset Management |
$132,500 |
$87,450 |
$45,050 |
2016-04-1 |
Edgewater |
Lake Baptiste Dam Upgrade Project |
$251,404 |
$165,926 |
$85,478 |
2017-07-1 |
Elkford |
Abruzzi Heights Infrastructure Replacement Design |
$140,000 |
$92,400 |
$47,600 |
2017-02-1 |
Enderby |
Shuswap River Water Main Crossing |
$329,700 |
$217,602 |
$112,098 |
2017-03-20 |
Fort Fraser |
Fort Fraser Infrastructure Improvement Project |
$1,868,304 |
$1,233,080 |
$635,225 |
2018-04-2 |
Fruitvale |
Beaver Valley Water System Davis/Eastview Improvements |
$108,150 |
$71,379 |
$36,771 |
2017-08-1 |
Gibsons |
Water Infrastructure Renewal Program |
$618,420 |
$408,157 |
$210,263 |
2017-05-1 |
Gibsons |
ISMP Update and Implementation |
$150,000 |
$99,000 |
$51,000 |
2017-01-1 |
Gold River |
Beneficial Biosolids Reuse |
$298,155 |
$196,782 |
$101,373 |
2017-05-1 |
Grand Forks |
City of Grand Forks Wastewater Treatment Facility Upgrades |
$2,005,000 |
$1,323,300 |
$681,700 |
2017-06-15 |
Grand Forks |
City of Grand Forks 2017 Sewer Phasing Plan |
$50,000 |
$33,000 |
$17,000 |
2017-01-16 |
Granisle |
Water Treatment Plant Detailed Design |
$106,018 |
$69,971 |
$36,047 |
2017-03-1 |
Greenwood |
Greenwood Wastewater Utility Renewal |
$350,000 |
$231,000 |
$119,000 |
2017-04-1 |
Harrison Hot Springs |
Harrison Hot Springs (HHS) Water Distribution Project |
$1,383,800 |
$913,308 |
$470,493 |
2017-05-1 |
Hatzic |
Electoral Area F - Hatzic Prairie Water System Upgrade |
$889,336 |
$586,962 |
$302,375 |
2017-08-15 |
Hazelton |
Bay Street Storm and Watermain Replacement |
$175,450 |
$115,797 |
$59,653 |
2017-06-1 |
Honeymoon Bay |
Mesachie Lake Wastewater Treatment and Collection Upgrade Project, Phase 1 (Area F) |
$738,896 |
$487,671 |
$251,226 |
2017-07-11 |
Houston |
Lagoon Outfall Upgrades |
$167,224 |
$110,368 |
$56,857 |
2017-07-15 |
Kamloops |
Juniper Creek Bank Stability |
$1,337,324 |
$882,633 |
$454,691 |
2017-10-2 |
Kamloops |
TNRD Utility Systems Master Plan |
$87,100 |
$57,486 |
$29,614 |
2017-04-1 |
Kaslo |
Kaslo Wastewater Treatment Plant Improvements |
$221,000 |
$145,860 |
$75,140 |
2017-09-1 |
Kelowna |
SEKID/SOMID Water Supply Project |
$26,450,000 |
$17,457,000 |
$8,993,000 |
2017-05-15 |
Kelowna |
Falcon Ridge Water System Improvement |
$362,700 |
$239,382 |
$123,318 |
2017-03-1 |
Keremeos |
Olalla Water System Rehabilitation Project |
$299,875 |
$197,917 |
$101,958 |
2017-06-19 |
Keremeos |
Village of Keremeos Water System Upgrades |
$788,050 |
$520,113 |
$267,937 |
2017-06-1 |
Kimberley |
Kimberley Wastewater Treatment Facility (WWTF) – Planning and Design |
$1,318,000 |
$869,880 |
$448,120 |
2017-01-1 |
Kitimat |
Water System Backup Power and Pump 6B upgrade |
$375,000 |
$247,500 |
$127,500 |
2017-05-3 |
Kootenay Boundary |
Rivervale and Oasis Sewer Service Pump Replacements |
$100,311 |
$66,205 |
$34,106 |
2017-06-1 |
Lake Country |
Eldorado Treated Water Reservoir & Glenmore Booster Station |
$3,500,000 |
$2,310,000 |
$1,190,000 |
2017-03-1 |
Lake Errock |
Electoral Area C Lake Errock Water System Upgrades |
$200,875 |
$132,577 |
$68,298 |
2017-10-2 |
Lions Bay |
Water Storage Facilities |
$1,355,500 |
$894,630 |
$460,870 |
2017-03-01 |
Logan Lake |
Water Distribution System Improvements |
$875,000 |
$577,500 |
$297,500 |
2017-04-1 |
Lumby |
Long-Term Wastewater Treatment Plant Upgrades |
$119,565 |
$78,912 |
$40,653 |
2017-03-1 |
Lumby |
Groundwater Supply Evaluation & Monitoring Well Construction |
$120,588 |
$79,588 |
$41,000 |
2017-01-9 |
Lund |
Lund Wastewater System Upgrade |
$280,000 |
$184,800 |
$95,200 |
2017-04-3 |
Lytton |
Village of Lytton Groundwater Development |
$1,300,000 |
$858,000 |
$442,000 |
2017-04-3 |
Lytton |
Village of Lytton Source Water Protection Planning |
$48,510 |
$32,016 |
$16,494 |
2016-12-1 |
Mackenzie |
District of Mackenzie Community Water Supply Well |
$399,000 |
$263,340 |
$135,660 |
2017-05-31 |
Maple Ridge |
225 Street Pump Station and Force Main Upgrade - Phase 1 |
$601,750 |
$397,155 |
$204,595 |
2017-04-1 |
Masset |
Masset Water Main R eplacement |
$495,609 |
$327,102 |
$168,508 |
2017-04-1 |
McBride |
Dominion Creek Drinking Water Intake Replacement |
$172,012 |
$113,528 |
$58,485 |
2017-06-1 |
Mission |
Fraser River Sanitary Crossing Siphon |
$4,155,436 |
$2,742,587 |
$1,412,849 |
2017-06-1 |
Mount Waddington |
Wastewater System Upgrades |
$270,585 |
$178,586 |
$91,999 |
2017-03-1 |
Mount Waddington |
Water System Upgrades |
$41,350 |
$27,291 |
$14,059 |
2017-05-1 |
Moyie |
Moyie Watermain Replacement Project |
$104,952 |
$69,268 |
$35,685 |
2017-05-15 |
Nanaimo |
Bowser Sewer Servicing |
$4,572,487 |
$3,017,841 |
$1,554,646 |
2017-11-1 |
Nakusp |
Galvanized Main Replacement |
$307,908 |
$203,219 |
$104,690 |
2017-03-15 |
New Hazelton |
13th Avenue Water Line Upgrade |
$405,250 |
$267,465 |
$137,785 |
2017-06-1 |
New Hazelton |
Wastewater Treatment Facility Assessment |
$15,300 |
$10,098 |
$5,202 |
2017-04-1 |
New Westminster |
Sapperton Combined Sewer Separation |
$3,326,172 |
$2,195,273 |
$1,130,899 |
2017-01-22 |
North Cowichan |
Crofton Alternate Water Supply |
$1,562,437 |
$1,031,208 |
$531,230 |
2017-07-15 |
North Okanagan |
Duteau Creek Water Treatment Plant UV Disinfection Addition |
$3,500,000 |
$2,310,000 |
$1,190,000 |
2017-07-1 |
North Vancouver |
Wastewater Inflow and Infiltration Program - Lynn Valley Area |
$1,760,000 |
$1,161,600 |
$598,400 |
2017-05-1 |
Northern Rockies |
Airport Watermain and Pump Station |
$2,790,000 |
$1,841,400 |
$948,600 |
2017-05-1 |
Oak Bay |
Water Main Extension & Secondary Connection Project |
$692,875 |
$457,297 |
$235,579 |
2017-05-1 |
Oak Bay |
Uplands Combined Sewer Separation Project - Detailed Design |
$195,758 |
$129,200 |
$66,558 |
2016-04-1 |
Okanagan Falls |
Okanagan Falls Sewer System Upgrade Project |
$23,282 |
$15,366 |
$7,916 |
2017-05-15 |
Okanagan Similkameen |
2017 Sun Valley Water System Upgrade Project |
$22,000 |
$14,520 |
$7,480 |
2017-05-15 |
Oliver |
Willowbrook Water System Improvement Project |
$19,550 |
$12,903 |
$6,647 |
2017-06-5 |
Oliver |
Watermain Looping at Head of Lake |
$281,500 |
$185,790 |
$95,710 |
2017-04-3 |
Osoyoos |
2017 Sanitary Sewer Infrastructure Rehabilitation Program |
$510,000 |
$336,600 |
$173,400 |
2017-01-15 |
Parksville |
Drinking Water Supply Transmission Mains and Secondary Membrane Water Treatment |
$3,652,487 |
$2,410,641 |
$1,241,846 |
2017-03-1 |
Parksville |
French Creek Pollution Control Centre Expansion |
$200,000 |
$132,000 |
$68,000 |
2017-03-1 |
|
|
|
|
||
Penticton |
Carmi Water Reservoir Storage Capacity Upgrade |
$707,500 |
$466,950 |
$240,550 |
2017-05-30 |
Penticton |
Naramata Water System Upgrade Project |
$2,217,351 |
$1,463,451 |
$753,901 |
2017-03-6 |
Port Alberni |
Somass Estuary (SE) Environmental Stewardship Protection Project |
$4,153,741 |
$2,741,469 |
$1,412,272 |
2017-01-7 |
Port Alice |
Port Alice Water Tank Replacement |
$230,100 |
$151,866 |
$78,234 |
2017-04-17 |
Port Edward |
Sanitary and Stormwater Pipe Rehabilitation |
$487,500 |
$321,750 |
$165,750 |
2017-06-1 |
Port Hardy |
District of Port Hardy Reservoir Project |
$2,500,000 |
$1,650,000 |
$850,000 |
2017-01-2 |
Port Moody |
Angela Drive & Cecile Drive - Utility & Roadworks Improvements |
$862,500 |
$569,250 |
$293,250 |
2017-04-17 |
Port Renfrew |
Port Renfrew Water Main Replacement |
$294,038 |
$194,065 |
$99,974 |
2017-08-1 |
Pouce Coupe |
Village Asset Management Assessment |
$25,000 |
$16,500 |
$8,500 |
2017-01-15 |
Powell River |
Consolidated Waste Water Treatment System |
$1,999,550 |
$1,319,703 |
$679,847 |
2017-06-1 |
Prince Rupert |
Woodworth Lake Dam Replacement Project |
$4,295,000 |
$2,834,700 |
$1,460,300 |
2017-07-1 |
Princeton |
Wastewater Treatment System Upgrading and Desludging |
$531,500 |
$350,790 |
$180,710 |
2017-05-1 |
Pritchard |
Pritchard Sewer Backup Generator and System Upgrade Project |
$57,250 |
$37,785 |
$19,465 |
2017-06-15 |
Qualicum Beach |
The Water and Wastewater Portion of the Memorial Upgrade Phase 3 |
$862,500 |
$569,250 |
$293,250 |
2017-06-1 |
Quesnel |
Drinking Water Supply and Storage Upgrades |
$1,804,450 |
$1,190,937 |
$613,513 |
2017-06-1 |
Revelstoke |
Illecillewaet River Waterline Crossing |
$585,562 |
$386,471 |
$199,092 |
2017-06-1 |
|
|
|
|
||
Rossland |
Spokane Street Infrastructure Improvement Project |
$2,188,029 |
$1,444,099 |
$743,930 |
2017-05-1 |
Rossland |
Comprehensive Sanitary Sewer Inflow & Infiltration Strategy |
$250,000 |
$165,000 |
$85,000 |
2017-03-15 |
Saanich |
CIPP Lining Saanich |
$1,750,005 |
$1,155,003 |
$595,003 |
2017-03-15 |
Salmo |
Sewage System Upgrade and Improvements |
$1,046,250 |
$690,525 |
$355,725 |
2017-05-1 |
Salmo |
Asset Inventory and Condition Assessment Upgrading |
$63,000 |
$41,580 |
$21,420 |
2016-12-5 |
Sayward |
Newcastle Creek Dam Rehabilitation Project |
$396,000 |
$261,360 |
$134,640 |
2017-06-1 |
Sechelt |
Sechelt Sanitary Sewer Expansion Project |
$1,757,790 |
$1,160,141 |
$597,649 |
2017-04-1 |
Sicamous |
Wastewater Facilities Upgrades |
$1,000,000 |
$660,000 |
$340,000 |
2017-04-1 |
Silverton |
Silverton Water Main Replacement Project |
$234,337 |
$154,662 |
$79,676 |
2017-07-1 |
Smithers |
Main Street to Victoria Drive Watermain Looping Project |
$282,500 |
$186,450 |
$96,050 |
2017-05-14 |
Sorrento |
Lakeview Place Subdivision Water System Connection Project |
$240,980 |
$159,046 |
$81,934 |
2017-04-15 |
Sparwood |
Water and Wastewater Infrastructure Network Study |
$125,000 |
$82,500 |
$42,500 |
2017-02-1 |
Squamish |
Water System Improvements |
$688,100 |
$454,146 |
$233,954 |
2017-07-01 |
Stewart |
Stewart Wastewater Rehabilitation Project |
$560,000 |
$369,600 |
$190,400 |
2017-01-4 |
Sun Peaks |
Sun Peaks – Sewage Treatment Plant Facilities Upgrades |
$1,207,500 |
$796,950 |
$410,550 |
2017-04-1 |
|
|
|
|
||
Sunshine Coast |
Merrill Crescent Community Septic Field System Replacement |
$32,500 |
$21,450 |
$11,050 |
2017-08-1 |
Sunshine Coast |
North Pender Harbour Water Systems Water Main Replacements |
$1,650,000 |
$1,089,000 |
$561,000 |
2017-06-1 |
Sunshine Coast |
Pender Harbour, Canoe Road Community Septic Field System Replacement |
$37,500 |
$24,750 |
$12,750 |
2017-07-1 |
Tahsis |
Community Water Conservation Project |
$204,451 |
$134,937 |
$69,515 |
2017-05-1 |
Tahsis |
Wastewater System Condition Assessment and Optimization |
$137,000 |
$90,420 |
$46,580 |
2017-04-3 |
Taylor |
Lift Station #3 Replacement Project |
$585,000 |
$386,100 |
$198,900 |
2017-07-15 |
Taylor |
Sludge Thickening Planning Project |
$15,100 |
$9,966 |
$5,134 |
2017-04-1 |
Telkwa |
Water Treatment Plant Assessment and Water Study Update |
$24,869 |
$16,413 |
$8,456 |
2016-11-1 |
Terrace |
Terrace Wastewater System Improvements |
$1,327,287 |
$876,009 |
$451,279 |
2017-04-1 |
Terrace |
Terrace Reservoir Capacity Improvement Design |
$100,000 |
$66,000 |
$34,000 |
2016-12-1 |
Tofino |
District of Tofino Wastewater Treatment Plant |
$875,000 |
$577,500 |
$297,500 |
2017-01-16 |
Trail |
Water Treatment Plant Regulatory Upgrades |
$623,540 |
$411,536 |
$212,004 |
2017-10-1 |
Trail |
Rivervale Water and Street Lighting Service Water System Intake Upgrades |
$46,080 |
$30,412 |
$15,668 |
2017-09-22 |
Trail |
Columbia Pollution Control Centre Upgrade to Secondary Treatment |
$786,000 |
$518,760 |
$267,240 |
2017-03-31 |
Tumbler Ridge |
Lagoon Aeration System - Phase II |
$535,300 |
$353,298 |
$182,002 |
2017-09-1 |
Ucluelet |
Wastewater Treatment Lagoon Rehabilitation |
$869,045 |
$573,569 |
$295,476 |
2016-06-15 |
Vancouver |
Vancouver South Sewer Separation Project |
$5,837,500 |
$3,852,750 |
$1,984,750 |
2017-02-22 |
Vanderhoof |
Water Supply and Storage Upgrades: Reservoir, Booster Station & Supply Main |
$1,789,750 |
$1,181,235 |
$608,515 |
2017-04-1 |
Vernon |
Okanagan Landing Sewer Extension Project |
$1,842,500 |
$1,216,050 |
$626,450 |
2017-05-15 |
Wells |
Water and Sewage Infrastructure |
$175,000 |
$115,500 |
$59,500 |
2017-06-5 |
West Kelowna |
Rose Valley Water Treatment Plant |
$24,700,000 |
$16,302,000 |
$8,398,000 |
2017-03-15 |
Whistler |
Emerald Water System Disinfection Upgrade |
$1,256,512 |
$829,298 |
$427,215 |
2017-05-1 |
Whistler |
Pinecrest Estates Wastewater Treatment Plant (Sewer) Replacement |
$998,205 |
$658,815 |
$339,390 |
2017-08-1 |
White Rock |
Arsenic and Manganese Water Treatment Project |
$7,102,500 |
$4,687,650 |
$2,414,850 |
2017-09-1 |
Williams Lake |
Stormwater Management Phase 4 |
$271,225 |
$179,008 |
$92,217 |
2017-06-1 |
Williams Lake |
Water Management Strategy |
$100,000 |
$66,000 |
$34,000 |
2017-01-3 |
Ymir |
Ymir Water Storage Reservoir Replacement |
$387,328 |
$255,636 |
$131,693 |
2017-05-1 |