Backgrounder: The governments of Canada and Newfoundland and Labrador invest in critical housing infrastructure

Backgrounder

Backgrounder: The governments of Canada and Newfoundland and Labrador invest in critical housing infrastructure

Canada Housing Infrastructure Fund Provincial (CHIF) and Territorial Agreement Stream

Newfoundland and Labrador will receive $123.1 million over 10 years under the Canada Housing Infrastructure Fund (CHIF) Provincial and Territorial Agreement Stream.

Recipient

Project Name

Project Details

Federal Funding

Newfoundland Labrador

10-year CHIF Provincial Agreement

Through this agreement, communities across Newfoundland and Labrador will be able to build or improve the critical infrastructure related to drinking water, wastewater, stormwater, and solid waste – that will in turn help them build more homes.

$123,148,269

Investing in Canada Infrastructure Program (ICIP)

The federal government is also investing $36,210,515 in the 73 water and wastewater projects through the Investing in Canada Infrastructure Program. The Government of Newfoundland and Labrador is investing $37,790,535 and municipalities are contributing a combined $12,772,187.

Project information:

Project descriptions can be found on the Housing and Infrastructure Project Map after 5 pm EDT on Friday, March 21.

Location

Project Name

Federal Funding

Provincial Funding

Municipal Funding

Appleton

Appleton - Watermain Replacement Circular/TCH

$239,404

$250,058

$50,012

Bay St. George South

Jeffrey's Pumphouse Improvements

$112,497

$140,622

$28,124

Belleoram

Water and Sewer Replacement

$290,187

$226,997

$45,399

Birchy Bay

Birchy Bay - Water Filtration System (AP-MCW-22196)

$175,192

$218,990

$43,798

Bishop's Falls

Turners Road Waterline and Sanitary Sewer Upgrades

$141,894

$98,319

$49,160

Bonavista

Lift Station Retrofits

$369,069

$369,069

$184,534

Botwood

Commonwealth Drive Watermain Replacement

$809,717

$1,012,146

$202,429

Burnt Islands

Lift Station Upgrades

$201,655

$181,367

$36,273

Campbellton

Waterline extension on Road to the Isles and Kingman/Decker Drive  (AP-MCW-23038)

$253,886

$0

$0

Cape St. George

Cape St. George Waterline Replacement

$181,267

$226,584

$45,317

Carmanville

Water and Sewer Services Phase 4

$439,383

$549,229

$109,846

Cartwright

Sanitary Sewer

$504,927

$631,158

$126,232

Channel-Port aux Basques

High Street Stormwater Rehabilitation

$258,798

$258,798

$129,399

Channel-Port aux Basques

Dennis Road Water Supply Booster Station

$265,342

$265,342

$132,671

Charlottetown (Labrador)

Water and Sewer, Phase 5.2 - Big Cove Extension

$993,811

$1,242,264

$248,453

Come By Chance

Water and Sewer Upgrading - Shaheen Crescent - Phase 2

$360,920

$451,150

$90,230

Daniel's Harbour

Replace Valves at Pumphouse

$22,450

$28,062

$5,612

Deer Lake

Main Lift Station Upgrades

$887,890

$887,890

$443,945

Deer Lake

Lift Station Upgrades - Church Street 

$115,405

$115,405

$57,703

Fermeuse

Future Sanitary Sewer - Phase 3

$171,458

$214,323

$42,865

Fermeuse

2022 Phase 2 of Sewer System Extension

$342,021

$427,526

$85,505

Flatrock

Red Head Road Ditching

$183,669

$229,586

$45,917

Fortune

Bunker Hill Road Water and Sewer - Phase ll

$341,221

$426,526

$85,305

Fortune

Bunker Hill Road Water and Sewer Phase 1

$394,768

$493,460

$98,692

Gander

Gander Pumphouse Upgrades to Improve Potable Water Efficiency, Reliability and Capacity

$1,722,805

$0

$0

George's Brook-Milton

Milton Watermain Replacement (Phase 3)

$253,914

$317,392

$63,478

Heart's Content

Installing 8 Inch Line from the S.U.F Hall on Main Road to Booster Pumping Station

$201,140

$251,426

$50,285

Humber Arm South

Webcon Road Storm Sewer System

$119,675

$149,593

$29,919

Humber Arm South

New Chlorination Building

$243,274

$304,093

$60,819

Indian Bay

Water & Sewer Upgrades - Phase I

$193,241

$241,552

$48,310

Isle aux Morts

Phase 4 - Water and Sewer Upgrades

$306,641

$383,302

$76,660

Labrador City

Storm Sewer Upgrades (Walsh River, Harrie Lake, Duley)

$563,048

$422,286

$422,286

L'Anse au Loup

Water Shed Dam Area Reconstruction

$247,017

$308,771

$61,754

Lewisporte

Water Tank Bypass Line and Intake Supply Line Repairs

$151,350

$151,350

$75,675

Logy Bay-Middle Cove-Outer Cove

Power's Lane Stream Crossing

$186,646

$233,308

$46,662

Lourdes

Town of Lourdes - Water Treatment Facility Improvements

$180,369

$225,461

$45,092

Makkovik

Chlorine Booster Station

$180,901

$0

$0

Marystown

Mayo's Road/Levi's Road Water, Sewer & Storm Sewer Upgrades (Phase 1)

$174,381

$174,381

$87,190

McIvers

Water Treatment System

$510,711

$638,389

$127,678

Meadows

Meadow Crescent Lift Station Replacement

$145,094

$181,367

$362,732

Middle Arm

Falls Road Water & Sewer

$158,086

$197,608

$39,522

Mount Pearl

Water, Sanitary and Storm Sewer, Asphalt, Curb and Sidewalk Replacement – Jackman Drive

$1,818,840

$1,364,130

$1,364,130

New-Wes-Valley

Water Treatment Plant

$4,045,934

$5,057,418

$1,011,484

New-Wes-Valley

Water Storage and Distribution System

$2,248,225

$2,810,281

$562,056

Norris Point

Lift Station #3

$127,506

$159,383

$31,877

Norris Point

Lift Station #1

$141,244

$159,383

$31,877

Norris Point

Lift Station #2

$127,506

$159,383

$31,877

North West River

2022 Storm Drainage Improvements

$211,901

$264,876

$52,975

Old Perlican

Septic System Installation

$167,884

$209,855

$41,971

Pasadena

Tipping Drive Water Lines Phase 2

$616,648

$616,648

$308,324

Pasadena

Lakeshore/Tipping Drive Sewer Installation

$471,554

$471,554

$235,777

Point Leamington

Water main phase 2

$362,658

$453,323

$90,665

Pool's Cove

Water System Improvements

$269,962

$337,452

$67,490

Port Saunders

Lift Station #3 and #4

$253,914

$317,392

$63,478

Portugal Cove-St. Philip's

St. Philips WWTP Treatment Expansion

$434,080

$325,560

$325,560

Rigolet

Lift Station and Force Main Upgrades

$251,758

$314,698

$62,940

Roddickton-Bide Arm

Bide Arm Water Supply Dam Replacement

$362,734

$453,417

$90,683

Sandy Cove

Barbour Avenue Water Main Extension

$193,341

$214,104

$42,821

Springdale

Main Street (Hemlock to Little Bay Road) Water, Sanitary Sewer and Storm Sewer Installation and Road Resurfacing

$609,467

$761,834

$152,367

St. Alban's

Main Street Water and Sewer Replacement - Phase 1

$902,029

$1,127,536

$225,507

St. Anthony

West Street Waterline Upgrading

$1,342,051

$1,677,563

$335,513

St. Bride's

Southside Dam Upgrade and Chlorination System

$214,141

$267,676

$53,535

St. John's

275 Southside Road Ditch Inlet & Storm Sewer

$725,468

$544,101

$544,101

St. Lunaire-Griquet

Replace Circular Road Watermain

$378,540

$473,175

$94,635

Steady Brook

Sewer Lagoon Upgrade

$939,824

$614,127

$122,826

Stephenville Crossing

Seal Cove Road Phase 5, Water Sewer and Storm Replacement

$626,269

$782,836

$156,567

Stephenville

Rose Avenue Reconstruction

$720,152

$720,152

$360,076

Stephenville

Main Street Reconstruction

$1,363,088

$1,363,088

$681,544

Swift Current

Hollet's Point Well water quality improvement

$7,255

$9,068

$1,814

Torbay

North Pond Water Treatment Plant - Phase 2

$1,088,202

$816,151

$816,151

Torbay

North Pond Water Treatment Plant - Phase 1

$344,597

$258,448

$258,448

Twillingate

Lift station retrofit - Coast Guard Sewage Lift Station and Smith's Lane

$253,914

$317,392

$63,478

Wabana

West Dam Water Supply Phase 4

$994,704

$1,243,380

$504,158

Page details